Primer Piece - "No Damage for Delay" Clauses
By: Jennifer M. Horn
As part of an ongoing series, Construction Law Signal will examine basic construction contract clauses and offer tips for navigating the nuanced arena that is the negotiated construction contract.
“No Damage for Delay” Clauses On Public Projects: In the Mid-Atlantic Region, Geography Matters
A “No Damage for Delay” provision is a classic construction clause that, if present in the contract, provides that where a contractor is delayed by an event that is not the contractor’s fault, the contractor’s remedy in that instance is limited to an extension of time – and no additional money is provided. However, more time can be little consolation to the contractor when every dollar counts. A myriad of issues can result in delay on a job site. Unforeseen subsurface site conditions can cause delay. These could include:
- Inclement weather;
- Acts of God;
- Design changes;
- Problems with obtaining access to one’s work site;
- Strikes and/or labor disputes; and
- Failure to have timely delivered material and equipment.
In addition, poor project coordination, the inability to mobilize adequate labor and/or delays caused by the actions or failure of another contractor to act on a project also frequently result in delay.
As a consequence, costs associated with delay may occur. These costs may manifest in the form of wage escalation, extended equipment costs, or inefficiency. Also, increased finance costs, extended job supervision and field overhead costs, and reduced profits are typical costs associated with delay.
In the realm of public contracts, where the contractor can not negotiate the terms of the contract, different states have reached different conclusions about the validity of the “no damage for delay” clauses that limit a contractor’s ability to recover money in addition to being granted an extension of time in which to perform the work. For instance, in New Jersey and Virginia, legislation provides that “no damage for delay” clauses are void against public policy.
In Maryland, Pennsylvania and Delaware, however, the validity of “no damage for delay” clauses has been upheld in various courts of law.In short, one must be cognizant of the controlling contractual jurisdiction before jumping to conclusions regarding the force and effect of “no damage for delay” clauses in a construction contract.
Jennifer M. Horn is Senior Counsel at Cohen Seglias and a member of the Construction Group. She concentrates her practice in the areas of construction litigation and real estate.

with a homeowner who serves as a “general contractor” on the project. In fact, such a contract is not only subject to the Consumer Fraud Act, but also to the Contractor’s Registration Act, and the Home Improvement Practices regulations adopted by the New Jersey Division of Consumer Affairs.
stories high and 800,000 square-feet, will be PNC’s largest building in Pittsburgh.
the country. Besides the work itself, benefits of an expanded geographic footprint include a broader client base, thereby creating mutually beneficial relationships.
r Vice President of the Office Services Group of 
immediately, and include
t is designed, among other things, to
of airport runways. He also called for an “infrastructure bank” that would focus on paying for national and regional transportation projects.
programs, as well as its commitment to renewable energy, have enabled it to reach this point.
ross the state. The Assembly Appropriations Committee is awaiting assurance from the Legislative Council that A1084 does not violate any New Jersey statutes. New Jersey’s school construction budget is one of the largest in the nation.
times. Even after investing time and labor, contractors and subcontractors face the possibility of not getting paid. To fully protect itself from a defaulting owner, a contractor or subcontractor must file a mechanics’ lien against the owner’s property once the work has been completed.
reluctance to approve a $1.25 billion sale of bonds to refinance up to $500 million for the nearly bankrupt
The New Jersey Superior Court recently issued an opinion that serves as a cautionary tale for all parties in a construction project who perform work without complete, signed copies of their contracts on hand. In the case of 

it is easy to presume that the solicitations or advertisements for certain types of contracts are consistent within the sa